28-08-2023

Energy Efficiency at CP: Contumil building

Project to improve energy and environmental performance

The building where several organisational units that support the operation are in the Contumil complex near Porto will undergo a transformation to increase its energy and other resource efficiency.

The project to improve the energy efficiency of the Contumil building aims to increase the building's energy rating from C to A by implementing several measures, such as changing the light fittings to LED technology, installing a boiler for domestic hot water and managing and monitoring electricity and water consumption.

After the intervention, it is estimated that the building, with a total area of 5,597.68 square metres, will have an Energy Efficiency Indicator of 101.6 kWhep / square metre per year, which, through a reduction in primary energy of around 26.56 tonnes of oil equivalent per year, will reduce primary energy consumption by 54.3%.

This project is co-financed by the Environmental Fund under the Recovery and Resilience Plan.

 

Project Name: TC-C13-i02: Energy Efficiency in Central Public Administration Buildings - Energy Efficiency in the CP: Contumil Building

Region of intervention: North

Beneficiary: CP - Comboios de Portugal E.P.E.

Start date: 01/02/2022

Completion date: 31/08/2024

Total eligible cost: €232,515

Financial support from the Environmental Fund (FA): €232,515

Programme: Recovery and Resilience Plan (PRR)

Funding organisation website: https://www.fundoambiental.pt/